Data Center Commissioning: Verizon Wireless

  
  
  
  
  
  

Verizon Wireless

Lee Technologies acted as the Commissioning Authority for the 70,000 square foot Verizon Wireless Multi-Switch Center located in Sunnyvale, California.

Lee Technologies was responsible for pre-startup verification, supervision of start-up and functional testing of three (3) 1500 kilowatt Generators, four (4) Automatic Transfer Switches, three (3) Manual Transfer Switches, seventeen (17) Computer Room Air Condition Units, as well as other electrical and mechanical equipment. Lee Technologies performed the commissioning and Integrated System Testing of the equipment on-site and prepared a final commissioning process report to verify that all project requirements were achieved